IEP Orchard BESS
ERCOT queue ID 23INR0556
| Queue ID | 23INR0556 |
|---|---|
| Project name | IEP Orchard BESS |
| Status (as published) | In Queue |
| Substation | Station Name (TDSP Station Code): OR Load/Load Transformer Name :TR1 PTI BUS number: Voltage in kV (Transmission Level): Project Size: 9.99 MW battery energy storage (BESS) system; 50 MWh connecting on CNP Distribution System. |
| Point of interconnection | Station Name (TDSP Station Code): OR Load/Load Transformer Name :TR1 PTI BUS number: 44541 Voltage in kV (Transmission Level): 138 kV Project Size: 9.99 MW battery energy storage (BESS) system; 50 MWh connecting on CNP 34.5kV Distribution System. |
| County | Fort Bend |
| State | TX |
| Voltage | 138 kV |
| Capacity | 10 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2026-09-18 |
| Source dataset | small |
Additional filed fields
| Interconnecting Entity | IEP Tejas Verde LLC |
|---|---|
| Cdr Zone | HOUSTON |
| Fuel Code | OTH |
| Technology Code | BA |
| Ia Signed | 45147 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.