Bee, TX interconnection queue

12 active projects totalling 1,839.4 MW in the ERCOT queue.

12active projects
1,839.4active MW
12total filed
Queue IDProjectkVMWResourceStatus
25INR0060 Argenta Solar 345 310 Solar SS Completed, FIS Started, IA
20INR0129 Foxtrot Wind 345 268.2 Wind SS Completed, FIS Completed, IA
28INR0485 Sparta BESS 345 251 Battery SS Completed, FIS Started, No IA
26INR0412 BumbleBee Solar 345 200.9 Solar SS Completed, FIS Started, No IA
27INR0372 Abeja Solar Farm 345 200.8 Solar SS Completed, FIS Started, IA
25INR0061 Argenta Storage 345 192 Battery SS Completed, FIS Started, IA
27INR0083 Spinner Energy Storage 138 125.6 Battery SS Completed, FIS Completed, No IA
26INR0134 Myers Solar 69 101.6 Solar SS Completed, FIS Started, No IA
26INR0135 Myers Storage 69 76 Battery SS Completed, FIS Started, No IA
22INR0559 Honeycomb Solar SLF 69 61.4 Solar SS Completed, FIS Completed, IA
25INR0394 Orchard Ray BESS 138 51.9 Battery SS Completed, FIS Started, No IA
23INR0392 Honeycomb Storage SLF 69 0 Battery SS Completed, FIS Completed, IA

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.