Substation Scout

Spinner Energy Storage

ERCOT queue ID 27INR0083

Queue ID27INR0083
Project nameSpinner Energy Storage
Status (as published)SS Completed, FIS Completed, No IA
SubstationPoesta Substation
Point of interconnection8196 Poesta Substation 138kV
CountyBee
StateTX
Voltage138 kV
Capacity125.6 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2029-07-10
Source datasetlarge

Additional filed fields

Interconnecting EntityGCI Wolf Energy Storage, LLC
Cdr ZoneSOUTH
Fuel CodeOTH
Technology CodeBA
Screening Study Complete45300
Fis Approved46045

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.