0 active projects totalling 0 MW in the BPA queue, plus 3 with terminal status (shown greyed).

0active projects
0active MW
3total filed
Queue IDProjectkVMWResourceStatus
G1051 Not reported 230 1,300 Solar WITHDRAWN
G1052 Not reported 230 1,300 Solar WITHDRAWN
G1056 Not reported 230 650 Battery WITHDRAWN

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with BPA before relying on these figures.