Substation Scout

Arlington Wind_Wheatfield Wind

BPA queue ID G95

Queue IDG95
Project nameArlington Wind_Wheatfield Wind
Status (as published)ENERGIZED
SubstationJones Canyon Substation
Point of interconnectionJones Canyon Substation
CountyGilliam
StateOR
VoltageNot reported
Capacity200 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2008-10-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorEDP Renewables North America LLC
Connection TypeGI
Interconnection TypeERIS
PoiJones Canyon Substation
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total200
Max Summer Mw200
Max Winter Mw200
Reason Not Completed.
Commentson-line November 2008 for 103 MW and February 2009 for 93 MW (LGIA split)

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.