Arlington Wind_Wheatfield Wind
BPA queue ID G95
| Queue ID | G95 |
|---|---|
| Project name | Arlington Wind_Wheatfield Wind |
| Status (as published) | ENERGIZED |
| Substation | Jones Canyon Substation |
| Point of interconnection | Jones Canyon Substation |
| County | Gilliam |
| State | OR |
| Voltage | Not reported |
| Capacity | 200 MW |
| Resource (as published) | Wind Turbine/Wind Turbine |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2008-10-01 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Requestor | EDP Renewables North America LLC |
|---|---|
| Connection Type | GI |
| Interconnection Type | ERIS |
| Poi | Jones Canyon Substation |
| Generator Type | Wind Turbine |
| Fuel Source | Wind Turbine |
| Nameplate Mw Total | 200 |
| Max Summer Mw | 200 |
| Max Winter Mw | 200 |
| Reason Not Completed | . |
| Comments | on-line November 2008 for 103 MW and February 2009 for 93 MW (LGIA split) |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.