Nine Canyon 2

BPA queue ID G73-01

Queue IDG73-01
Project nameNine Canyon 2
Status (as published)ENERGIZED
SubstationMcNary-Badger Canyon line (Nine Canyon Substation)
Point of interconnection115 kV McNary-Badger Canyon line (Nine Canyon Substation)
CountyBenton
StateWA
Voltage115 kV
Capacity32 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2007-11-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorEnergy Northwest (CGS)
Connection TypeGI
Interconnection TypeERIS
Poi115 kV McNary-Badger Canyon line (Nine Canyon Substation)
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total32
Max Summer Mw32
Max Winter Mw32
Reason Not Completed.
Commentson-line January 2008; reduced request from 100 MW

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.