Not reported

BPA queue ID G0724

Queue IDG0724
Project nameNot reported
Status (as published)STUDY
SubstationFairview-Rogue No 1 line.
Point of interconnectionFairview-Rogue No 1 230 KV line.
CountyCurry
StateOR
Voltage230 kV
Capacity280 MW
Resource (as published)Battery/Energy Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2026-12-10
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiFairview-Rogue No 1 230 KV line.
Generator TypeEnergy Storage
Fuel SourceBattery
Nameplate Mw Total280
Max Summer Mw280
Max Winter Mw280
ClusterTransition Late Stage
Reason Not Completed.
Commentsgrid-charging