Substation Scout

Not reported

BPA queue ID G0713

Queue IDG0713
Project nameNot reported
Status (as published)STUDY
SubstationBPA's Slatt Substation
Point of interconnectionBPA's Slatt Substation
CountyMorrow
StateOR
VoltageNot reported
Capacity100 MW
Resource (as published)Solar/Photovoltaic
Resource categorySolar (normalised for filtering)
Target commercial operation2026-12-31
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeERIS
PoiBPA's Slatt Substation
Generator TypePhotovoltaic
Fuel SourceSolar
Nameplate Mw Total100
Max Summer Mw100
Max Winter Mw100
Reason Not Completed.

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.