Decatur Island Battery Storage
BPA queue ID G0631
| Queue ID | G0631 |
|---|---|
| Project name | Decatur Island Battery Storage |
| Status (as published) | ENERGIZED |
| Substation | Decatur Substation |
| Point of interconnection | Decatur Substation |
| County | San Juan |
| State | WA |
| Voltage | Not reported |
| Capacity | 2 MW |
| Resource (as published) | Battery/Energy Storage |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2018-06-15 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Requestor | Orcas Power & Light Cooperative |
|---|---|
| Connection Type | GI |
| Interconnection Type | ERIS |
| Poi | Decatur Substation |
| Generator Type | Energy Storage |
| Fuel Source | Battery |
| Nameplate Mw Total | 2 |
| Max Summer Mw | 2 |
| Max Winter Mw | 2 |
| Reason Not Completed | . |
| Comments | Submitted as a 1.5 MW Request |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.