Substation Scout

Decatur Island Solar

BPA queue ID G0587

Queue IDG0587
Project nameDecatur Island Solar
Status (as published)ENERGIZED
SubstationDecatur Substation
Point of interconnectionDecatur Substation
CountySan Juan
StateWA
VoltageNot reported
Capacity1 MW
Resource (as published)Solar/Photovoltaic
Resource categorySolar (normalised for filtering)
Target commercial operation2018-06-15
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorOrcas Power & Light Cooperative
Connection TypeGI
Interconnection TypeERIS
PoiDecatur Substation
Generator TypePhotovoltaic
Fuel SourceSolar
Nameplate Mw Total1
Max Summer Mw1
Max Winter Mw1
Reason Not Completed.
CommentsSubmitted as a 350 kW request