Ridge Road Station

Named in 3 PJM planning documents for 1 project, from January 16, 2025 to October 8, 2025.

Existingdescribed as
PSEGzone
69kVkV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
PSE&G Transmission Zone M-3 Process South Brunswick
PSEG-2024-0005 · s3570
Engineering $3.4M 06/30/2026 35 MW 2025-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 06/2026 → 06/30/2026 2024-12-12 2025-01-16
Status conceptual (Conceptual) → engineering (Engineering and Planning) 2025-01-16 2025-10-08

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Mid-Atlantic
PSEG local plan submission for 2025 RTEP p. 5
PSE&G Transmission Zone M-3 Process South Brunswick “Cut and loop 69kV line from Ridge Road Station to West Windsor Station into customer’s new station.”
69kV
2025-10-08 TEAC
Informational Only - PSEG Local Plan Submission of the Supplemental Projects for 2025 p. 5
PSE&G Transmission Zone M-3 Process South Brunswick “Cut and loop 69kV line from Ridge Road Station to West Windsor Station into customer’s new station.”
69kV
2025-01-16 SRRTEP Mid-Atlantic
Item 02 - PSEG Supplemental Projects p. 6
PSE&G Transmission Zone M-3 Process South Brunswick No role wording
69kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.