Substation Scout

Roanoke

Named in 2 PJM planning documents for 2 projects, from December 3, 2024 to January 7, 2025.

Existingdescribed as
PJM system-widezone
138 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Recommended Solution: 2024-W1-81
b4000.200
Not printed 63.98 M 12/31/2029 Not printed 2025-01-07
TEAC
2024W1 – Regional Cluster Preferred Solution: 2024-W1-81
2024-W1-81
Not printed $137.02 M 12/31/2029 Not printed 2024-12-03
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$137.02M → 63.98 M 2025-01-07 2025-01-07
Cost estimate 63.98 M → $4.5 M 2025-01-07 2025-08-05
In-service date 12/31/2029 → 6/1/2029 2025-01-07 2025-08-05
Substations named ALTAVISTA; BROADFORD; CANDLERS MOUNTAIN; CLAYTOR; CLOVERDALE; FIELDALE; GOMINGO; GRASSY HILL; JACKSONS FERRY; JOHNSON MOUNTAIN; JOSHUA FALLS; LEESVILLE; MONEL; MONETA; MUSEVILLE; NEW LONDON; OAK LEVEL; OPOSSUM CREEK; OPPOSUM CREEK; OTTER; REDEYE; REUSENS; ROANOKE; ROCK CASTLE; S CHRISTIANSBURG; SMITH MOUNTAIN; TECH DRIVE; THORNTON → BROADFORD 2025-01-07 2025-08-05

Every mention

DateDocumentProjectWhat the document says about it
2025-01-07 TEAC
Item 12 - Reliability Analysis Update p. 73
Recommended Solution: 2024-W1-81 “Roanoke 138 kV Station Upgrade”
138 kV
2024-12-03 TEAC
Item 11 - Reliability Analysis Update p. 84
2024W1 – Regional Cluster Preferred Solution: 2024-W1-81 “Roanoke 138 kV Station Upgrade”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this