Georgetown

Named in 2 PJM planning documents for 1 project, from June 5, 2025 to September 9, 2025.

Not stateddescribed as
PEPCOzone
69 kV, 69kVkV as printed
2mentions

Also printed as: Georgetown Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Champlain Substation
PEP-2025-003
Engineering $590M 7/1/2029 Not printed 2025-09-09
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named F STREET; GEORGETOWN; I STREET; L STREET → CHAMPLAIN; F STREET; GEORGETOWN; I STREET; L STREET; TAKOMA 2025-06-05 2025-09-09

Every mention

DateDocumentProjectWhat the document says about it
2025-09-09 TEAC
Item 11 - PEPCO Supplemental Projects p. 4
Champlain Substation No role wording
69kV
2025-06-05 TEAC
Item 07 - PEPCO Supplemental Projects p. 3
Champlain Substation No role wording
69 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.