Whetstone

Named in 5 PJM planning documents for 2 projects, from October 8, 2024 to October 6, 2026.

Existingdescribed as
PENELECzone
115 kVkV as printed
5mentions

Also printed as: Whetstone 115 kV Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dubois - Harvey Run - Whetstone 115 kV Line Rehab
PN-2018-001 · s1769
Not printed $39.3M 6/29/2030 Not printed 2026-10-06
TEAC
Dubois – Whetstone 115 kV Misoperation Relays
PN-2023-015 · s3410.1
Not printed $2.1M 11/29/2023 Not printed 2024-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$5.3M → $39.3M Not reported Not reported
Cost estimate
prior value printed on the same page
$5.3M → $39.3M 2026-07-17 2026-07-17
Cost estimate
prior value printed on the same page
$5.3M → $39.3M 2026-10-06 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Penelec Local Plan Submission of Supplemental Projects for 2026 p. 3
Dubois - Harvey Run - Whetstone 115 kV Line Rehab “Whetstone 115 kV Substation – Terminal equipment to be replaced includes:”
115 kV
2026-10-01* SRRTEP Mid-Atlantic
Penelec local plan submission for 2026 RTEP p. 3
Dubois - Harvey Run - Whetstone 115 kV Line Rehab “Whetstone 115 kV Substation – Terminal equipment to be replaced”
115 kV
2026-09-08* SRRTEP Mid-Atlantic
Penelec local plan submission for 2024 RTEP p. 33
Dubois – Whetstone 115 kV Misoperation Relays “Replace wave trap, CCVT, line tuners, arresters, and relaying at Whetstone 115 kV Substation”
115 kV
2026-07-17 SRRTEP Mid-Atlantic
Item 04 - Penelec Supplemental Projects p. 4
Dubois - Harvey Run - Whetstone 115 kV Line Rehab “Whetstone 115 kV Substation – Terminal equipment to be replaced includes”
115 kV
2024-10-08 TEAC
Informational Only - PENELEC Local Plan submission of supplemental project 2024 p. 33
Dubois – Whetstone 115 kV Misoperation Relays “Replace wave trap, CCVT, line tuners, arresters, and relaying at Whetstone 115 kV Substation”
115 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.