Springboro

Named in 2 PJM planning documents for 2 projects, from September 18, 2025 to October 6, 2026.

Not stateddescribed as
PENELECzone
115 kVkV as printed
4mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Edinboro South Substation
PN-2023-006 · s3745.1
Not printed $13.57M 6/18/2027 Not printed 2026-10-06
TEAC
Morgan Street Substation
PN-2023-008 · s3746.1
Not printed $26.91M 12/3/2027 Not printed 2026-10-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Penelec Local Plan Submission of Supplemental Projects for 2026 p. 12
Edinboro South Substation No role wording
115 kV
2026-10-06 TEAC
Informational Only - Penelec Local Plan Submission of Supplemental Projects for 2026 p. 14
Morgan Street Substation No role wording
115 kV
2025-09-18 SRRTEP Mid-Atlantic
Item 05 - PENELEC Supplemental Projects p. 3
Edinboro South Substation No role wording
115 kV
2025-09-18 SRRTEP Mid-Atlantic
Item 05 - PENELEC Supplemental Projects p. 5
Morgan Street Substation No role wording
115 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this