Edinboro South

Named in 3 PJM planning documents for 2 projects, from September 18, 2025 to October 6, 2026.

Existingdescribed as
PENELECzone
115 kVkV as printed
6mentions

Also printed as: Edinboro South Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Edinboro South Substation
PN-2023-006 · s3745.1
Not printed $13.57M 6/18/2027 Not printed 2026-10-06
TEAC
Morgan Street Substation
PN-2023-008 · s3746.1
Not printed $26.91M 12/3/2027 Not printed 2026-10-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Penelec Local Plan Submission of Supplemental Projects for 2026 p. 13
Edinboro South Substation “Convert the Edinboro South Substation into a four-breaker ring bus.”
115 kV
2026-10-06 TEAC
Informational Only - Penelec Local Plan Submission of Supplemental Projects for 2026 p. 15
Morgan Street Substation “Adjust relay settings at Geneva and Edinboro South substations.”
115 kV
2026-10-01* SRRTEP Mid-Atlantic
Penelec local plan submission for 2026 RTEP p. 13
Edinboro South Substation “Convert the Edinboro South Substation into a four-breaker ring bus”
2026-10-01* SRRTEP Mid-Atlantic
Penelec local plan submission for 2026 RTEP p. 15
Morgan Street Substation “Adjust relay settings at Geneva and Edinboro South substations”
2025-09-18 SRRTEP Mid-Atlantic
Item 05 - PENELEC Supplemental Projects p. 3
Edinboro South Substation “Convert the Edinboro South Substation into a four-breaker ring bus”
2025-09-18 SRRTEP Mid-Atlantic
Item 05 - PENELEC Supplemental Projects p. 5
Morgan Street Substation “Adjust relay settings at Geneva and Edinboro South substations”
115 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.