Edinboro South
Named in 3 PJM planning documents for 2 projects, from September 18, 2025 to October 6, 2026.
Existingdescribed as
PENELECzone
115 kVkV as printed
6mentions
Also printed as: Edinboro South Substation
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Edinboro South Substation PN-2023-006 · s3745.1 |
Not printed | $13.57M | 6/18/2027 | Not printed | 2026-10-06 TEAC |
| Morgan Street Substation PN-2023-008 · s3746.1 |
Not printed | $26.91M | 12/3/2027 | Not printed | 2026-10-06 TEAC |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-10-06 | TEAC Informational Only - Penelec Local Plan Submission of Supplemental Projects for 2026 p. 13 |
Edinboro South Substation | “Convert the Edinboro South Substation into a four-breaker ring bus.” 115 kV |
| 2026-10-06 | TEAC Informational Only - Penelec Local Plan Submission of Supplemental Projects for 2026 p. 15 |
Morgan Street Substation | “Adjust relay settings at Geneva and Edinboro South substations.” 115 kV |
| 2026-10-01* | SRRTEP Mid-Atlantic Penelec local plan submission for 2026 RTEP p. 13 |
Edinboro South Substation | “Convert the Edinboro South Substation into a four-breaker ring bus” |
| 2026-10-01* | SRRTEP Mid-Atlantic Penelec local plan submission for 2026 RTEP p. 15 |
Morgan Street Substation | “Adjust relay settings at Geneva and Edinboro South substations” |
| 2025-09-18 | SRRTEP Mid-Atlantic Item 05 - PENELEC Supplemental Projects p. 3 |
Edinboro South Substation | “Convert the Edinboro South Substation into a four-breaker ring bus” |
| 2025-09-18 | SRRTEP Mid-Atlantic Item 05 - PENELEC Supplemental Projects p. 5 |
Morgan Street Substation | “Adjust relay settings at Geneva and Edinboro South substations” 115 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.