Molly Substation

Named in 3 PJM planning documents for 1 project, from March 18, 2026 to October 6, 2026.

Existingdescribed as
PENELECzone
46 kVkV as printed
3mentions

Also printed as: Molly

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Lewistown Area 46 kV Network
PN-2024-023 · s3984.1
Not printed $6.61M 12/31/2027 Not printed 2026-10-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Penelec Local Plan Submission of Supplemental Projects for 2026 p. 29
Lewistown Area 46 kV Network “Install a fourth 46 kV circuit breaker in the ring bus at Molly Substation.”
46 kV
2026-10-01* SRRTEP Mid-Atlantic
Penelec local plan submission for 2026 RTEP p. 29
Lewistown Area 46 kV Network “Install a fourth 46 kV circuit breaker in the ring bus at Molly Substation”
46 kV
2026-03-18 SRRTEP Mid-Atlantic
Item 08 - Penelec Supplemental Projects p. 6
Lewistown Area 46 kV Network “Install a fourth 46 kV circuit breaker in the ring bus at Molly Substation.”
46 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.