East Towanda

Named in 4 PJM planning documents for 2 projects, from October 8, 2024 to September 17, 2026.

Existingdescribed as
PENELECzone
115 kVkV as printed
4mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
East Sayre – East Towanda 115 kV Line: New Customer
PN-2023-012 · s3292.1
Not printed $1.67M 09/30/2025 Not printed 2024-10-08
TEAC
East Towanda - North Meshoppen 115 kV Line – Customer Connection
PN-2025-008
Conceptual $16.00 M 07/20/2029 Not printed 2026-09-17
SRRTEP Mid-Atlantic

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 12/31/2026 → 07/20/2029 2025-11-13 2026-09-17

Every mention

DateDocumentProjectWhat the document says about it
2026-09-17 SRRTEP Mid-Atlantic
Item 03 - Penelec Supplemental Projects p. 4
East Towanda - North Meshoppen 115 kV Line – Customer Connection “Adjust relay settings at East Towanda and North Meshoppen substations.”
2026-09-08* SRRTEP Mid-Atlantic
Penelec local plan submission for 2024 RTEP p. 16
East Sayre – East Towanda 115 kV Line: New Customer No role wording
115 kV
2025-11-13 SRRTEP Mid-Atlantic
Item 05 - Penelec Supplemental Projects p. 3
East Towanda - North Meshoppen 115 kV Line – Customer Connection No role wording
115 kV
2024-10-08 TEAC
Informational Only - PENELEC Local Plan submission of supplemental project 2024 p. 16
East Sayre – East Towanda 115 kV Line: New Customer No role wording
115 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.