West Reading

Named in 3 PJM planning documents for 1 project, from March 18, 2026 to October 6, 2026.

Existingdescribed as
METEDzone
69 kVkV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
South Reading - West Reading 69 kV Line
ME-2024-002 · s3975.1
Not printed $17.10M 12/29/2028 Not printed 2026-10-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-07* SRRTEP Mid-Atlantic
Met-Ed local plan submission for 2026 RTEP p. 15
South Reading - West Reading 69 kV Line “West Reading: Replace 69 kV Circuit Breaker 2602, Switches 2604 & 2605, and Relaying.”
2026-10-06 TEAC
Informational Only - MetEd Local Plan Submission of Supplemental Projects for 2026 p. 14
South Reading - West Reading 69 kV Line “West Reading: Replace 69 kV Circuit Breaker 2602, Switches 2604 & 2605, and Relaying”
2026-03-18 SRRTEP Mid-Atlantic
Item 07 - MetEd Supplemental Projects p. 6
South Reading - West Reading 69 kV Line “West Reading: Replace 69 kV Circuit Breaker 2602, Switches 2604 & 2605, and Relaying.”
69 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.