Belfast
Named in 3 PJM planning documents for 1 project, from January 16, 2025 to October 8, 2025.
Existingdescribed as
METEDzone
115 kVkV as printed
3mentions
Also printed as: Belfast Substation
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Belfast Substation ME-2024-014 · s3626.1 |
Not printed | $14.3M | 6/1/2028 | 78 MW | 2025-10-08 TEAC |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-09-08* | SRRTEP Mid-Atlantic Met-Ed local plan submission for 2025 RTEP p. 13 |
Belfast Substation | “Construct a four breaker 115 kV ring bus at Belfast Substation:” 115 kV |
| 2025-10-08 | TEAC Informational Only - MetEd Local Plan Submission of the Supplemental Projects for 2025 p. 13 |
Belfast Substation | “Construct a four breaker 115 kV ring bus at Belfast Substation:” 115 kV |
| 2025-01-16 | SRRTEP Mid-Atlantic Item 01 - MetEd Supplemental Projects p. 4 |
Belfast Substation | “Construct a four breaker 115 kV ring bus at Belfast Substation” 115 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.