Substation Scout

Roberts Road

Named in 1 PJM planning document for 1 project, on October 16, 2026.

Not stateddescribed as
JCPLzone
34.5 kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Taylor Lane Substation
JCPL-2026-048
Not printed Not printed Not printed Not printed 2026-10-16
SRRTEP Mid-Atlantic

Every mention

DateDocumentProjectWhat the document says about it
2026-10-16 SRRTEP Mid-Atlantic
Item 06 - JCPL Supplemental Projects Presentation p. 4
Taylor Lane Substation No role wording
34.5 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this