Substation Scout

Rand Blvd

Named in 1 PJM planning document for 1 project, on July 17, 2026.

Not stateddescribed as
JCPLzone
34.5 kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Morris Park Substation - 34.5 kV Breakers, NJ
JCPL-2026-038
Not printed Not printed Not printed Not printed 2026-07-17
SRRTEP Mid-Atlantic

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named CAPTIVE PLACE TAP; MARBLE HILL; MORRIS PARK; PHILIPSBURG; RAND BLVD; WARREN GLEN SWPT → MARBLE HILL; MORRIS PARK; PHILIPSBURG; WARREN GLEN SWPT 2026-07-17 2026-09-17

Every mention

DateDocumentProjectWhat the document says about it
2026-07-17 SRRTEP Mid-Atlantic
Item 02 - JCPL Supplemental Projects p. 4
Morris Park Substation - 34.5 kV Breakers, NJ No role wording
34.5 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this