Named in 1 PJM planning document for 1 project, on April 14, 2026.

Not stateddescribed as
JCPLzone
34.5 kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Cozy Lake - Franklin 34.5 kV S747 Line
JCPL-2026-013
Not printed Not printed Not printed Not printed 2026-04-14
SRRTEP Mid-Atlantic

Every mention

DateDocumentProjectWhat the document says about it
2026-04-14 SRRTEP Mid-Atlantic
Item 02 - JCPL Supplemental Projects p. 3
Cozy Lake - Franklin 34.5 kV S747 Line No role wording
34.5 kV