East Villa Rica

Named in 4 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
GPC, GTCproject sponsor
4projects in the plan

Described as new. The quoted wording calls this substation new. “new East Villa Rica Switching Station” — TEAMS 21069, plan p.184

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
GTC: GARRETT RD - V. RICA 230kV LINE RECONDUCTOR NETWORK IMPROV
Reconductor the section from East Villa Rica Switching station to Garrett Rd with 160C 1351 ACSS on 11.5 miles of the Garrett Road - Villa Rica 230kV line. Additionally, the 2.5 miles section from East Villa Rica Switching Station to Villa Rica will be rebuilt with bundled 200C 1351 ACSS Martin.
TEAMS 20505 · plan p.131 · zone 201
GTC In the plan
p.11
Jun 1, 2027 No change East Villa Rica, GARRETT RD, Garrett Road, RICA, Villa Rica
CC - EAST VILLA RICA SWITCHING STATION (IMPROVEMENTS)
Build a switching station along the right of way of the (3) 230kV lines about 2.5 miles East of Villa Rica. All three lines will terminate into this station.
TEAMS 20797 · plan p.157 · zone 201
GPC In the plan
p.12
Jun 1, 2028 No change East Villa Rica
SMART VALVES AT EAST VILLA RICA SWITCHING STATION
Install Advanced Power Flow Controllers at the new East Villa Rica Switching Station on the Douglasville - Villa Rica 230kV and Summer Lake - Villa Rica 230kV lines.
TEAMS 21069 · plan p.184 · zone 201
GPC In the plan
p.14
Jun 1, 2028 No change Douglasville, East Villa Rica, Summer Lake, Villa Rica
GTC: DOUGLASVILLE - EAST VILLA RICA SS 230kV REBUILD
Rebuild 8.2 miles of the Douglasville - East Villa Rica 230kV line with 200C 1351.0 ACSS Martin conductor.
TEAMS 21271 · plan p.247 · zone 201
GTC In the plan
p.18
Jun 1, 2030 New project Douglasville, East Villa Rica, EAST VILLA RICA SS

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.