Substation Scout

Garrett Road

Named in 2 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
230kV in the quote
GPC, GTCproject sponsor
2projects in the plan

Described as new. The quoted wording calls this substation new. “new Garrett Road 230kV switching station” — TEAMS 20243, plan p.115

The plan prints no county for this substation, and no utility project page found names one for it.

Location

Cobb County, GA

County of the road it is named for. No source prints a location. The county is that of the road the substation is named for, which lies in one county and fits the lines the plan connects to it. No point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

County: Garrett Road lies in Cobb County. Georgia has roads of that name in Carroll, Gwinnett, Hall, Polk and Cobb counties; only the Cobb one lies between Villa Rica and West Marietta, the 230kV line the plan splits for the new Garrett Road switching station.

Sources: 2025 GA ITS Ten-Year Plan (2026-2035), Southern Company Services; filed by Georgia Power in GA PSC Docket 56002 (2025 Annual Transmission Update, public disclosure) (filed 2026-02-27), p.115 · SERTP 2025 Regional Transmission Plan, SOUTHERN Balancing Authority Area project list (2025), p.64 · SERTP 2026 preliminary expansion plan project list (2026-06-12), p.28 · OpenStreetMap: Villa Rica Substation (way 159758304, 500/230/115/46 kV); no Douglasville, West Marietta or Trae Lane station mapped by name (OSM base 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
CC - GARRETT ROAD 230kV SS (NETWORK IMPROVEMENTS)
Build the new Garrett Road 230kV switching station splitting the Villa Rica - West Marietta 230kV line. Build a new 230kV line from the Trae Lane substation to the Garrett Road switching substation with bundled 100C 1351 ACSR conductor.
TEAMS 20243 · plan p.115 · zone 201
GPC In the plan
p.9
Dec 31, 2026 Delayed within 2026 Garrett Road, Trae Lane, Villa Rica, West Marietta
GTC: GARRETT RD - V. RICA 230kV LINE RECONDUCTOR NETWORK IMPROV
Reconductor the section from East Villa Rica Switching station to Garrett Rd with 160C 1351 ACSS on 11.5 miles of the Garrett Road - Villa Rica 230kV line. Additionally, the 2.5 miles section from East Villa Rica Switching Station to Villa Rica will be rebuilt with bundled 200C 1351 ACSS Martin.
TEAMS 20505 · plan p.131 · zone 201
GTC In the plan
p.11
Jun 1, 2027 No change East Villa Rica, GARRETT RD, Garrett Road, RICA, Villa Rica

Generation interconnection requests filed in Cobb, GA: Southern Company queue, 2 active of 2. Same county, not the same substation.

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.