Named in 3 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
GPC, GTCproject sponsor
3projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
GTC: DOUGLASVILLE - VILLA RICA 230kV REBUILD (CC NET IMPRVT)
Rebuild a 2.5 miles section of the Villa Rica - Douglasville 230kV line with bundled 200C 1351 ACSS Martin conductor.
TEAMS 20776 · plan p.127 · zone 201
GTC In the plan
p.10
Jun 1, 2027 No change Douglasville, Villa Rica
SMART VALVES AT EAST VILLA RICA SWITCHING STATION
Install Advanced Power Flow Controllers at the new East Villa Rica Switching Station on the Douglasville - Villa Rica 230kV and Summer Lake - Villa Rica 230kV lines.
TEAMS 21069 · plan p.184 · zone 201
GPC In the plan
p.14
Jun 1, 2028 No change Douglasville, East Villa Rica, Summer Lake, Villa Rica
GTC: DOUGLASVILLE - EAST VILLA RICA SS 230kV REBUILD
Rebuild 8.2 miles of the Douglasville - East Villa Rica 230kV line with 200C 1351.0 ACSS Martin conductor.
TEAMS 21271 · plan p.247 · zone 201
GTC In the plan
p.18
Jun 1, 2030 New project Douglasville, East Villa Rica, EAST VILLA RICA SS

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first