Hill View
Named in 2 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).
Described as new. The quoted wording calls this substation new. “new Great Valley and Hill View 230kV substations” — TEAMS 20151, plan p.114
The plan prints no county for this substation, and no utility project page found names one for it.
Location
On a named line, no point. No point is published. The planning documents place it on the transmission line named in the quote above, and both ends of that line are located. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
Note: The plan's line end is "Cartersville"; OSM's only Cartersville-named 230 kV station is "Cartersville Primary Substation" (Georgia Power), used as that end.
Sources: 2025 GA ITS Ten-Year Plan (2026-2035), Southern Company Services; filed by Georgia Power in GA PSC Docket 56002 (2025 Annual Transmission Update, public disclosure) (filed 2026-02-27), p.121 · 2025 GA ITS Ten-Year Plan (2026-2035), Southern Company Services; filed by Georgia Power in GA PSC Docket 56002 (2025 Annual Transmission Update, public disclosure) (filed 2026-02-27), p.114 · Georgia Power, Cash Creek–McGrau Ford 500 kV Transmission Project page (n/a (retrieved 2026-11-20)), About the Project; Project Map · OpenStreetMap: Cartersville Primary and McGrau Ford substations; 230 kV line way 178742241 (OSM base 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| CC - HILL VIEW & GRASSY HOLLOW SUB - IMPROVEMENTS Build two 230kV switching stations (Hill View and Grassy Hollow) looping into the Cartersville - McGrau Ford 230kV line. Build two new 230kV lines: Cass Pine - Great Valley and Great Valley - Grassy Hollow. TEAMS 20150 · plan p.121 · zone 211 |
GPC | In the plan p.10 |
Jun 1, 2027 | Advanced within 2027 | Cartersville, Grassy Hollow, Hill View, McGrau Ford |
| CC - CASS PINE 230/25kV NEW SUB IMPROVEMENTS Build a new 230/25kV networked substation named Cass Pine in Bartow County that will interconnect between new Great Valley and Hill View 230kV substations. TEAMS 20151 · plan p.114 · zone 211 |
GPC | In the plan p.9 |
Dec 31, 2026 | No change | Cass Pine, Great Valley, Hill View |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.