Hill View

Named in 2 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
230kV in the quote
GPCproject sponsor
2projects in the plan

Described as new. The quoted wording calls this substation new. “new Great Valley and Hill View 230kV substations” — TEAMS 20151, plan p.114

The plan prints no county for this substation, and no utility project page found names one for it.

Location

On a named line, no point. No point is published. The planning documents place it on the transmission line named in the quote above, and both ends of that line are located. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

Note: The plan's line end is "Cartersville"; OSM's only Cartersville-named 230 kV station is "Cartersville Primary Substation" (Georgia Power), used as that end.

Sources: 2025 GA ITS Ten-Year Plan (2026-2035), Southern Company Services; filed by Georgia Power in GA PSC Docket 56002 (2025 Annual Transmission Update, public disclosure) (filed 2026-02-27), p.121 · 2025 GA ITS Ten-Year Plan (2026-2035), Southern Company Services; filed by Georgia Power in GA PSC Docket 56002 (2025 Annual Transmission Update, public disclosure) (filed 2026-02-27), p.114 · Georgia Power, Cash Creek–McGrau Ford 500 kV Transmission Project page (n/a (retrieved 2026-11-20)), About the Project; Project Map · OpenStreetMap: Cartersville Primary and McGrau Ford substations; 230 kV line way 178742241 (OSM base 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
CC - HILL VIEW & GRASSY HOLLOW SUB - IMPROVEMENTS
Build two 230kV switching stations (Hill View and Grassy Hollow) looping into the Cartersville - McGrau Ford 230kV line. Build two new 230kV lines: Cass Pine - Great Valley and Great Valley - Grassy Hollow.
TEAMS 20150 · plan p.121 · zone 211
GPC In the plan
p.10
Jun 1, 2027 Advanced within 2027 Cartersville, Grassy Hollow, Hill View, McGrau Ford
CC - CASS PINE 230/25kV NEW SUB IMPROVEMENTS
Build a new 230/25kV networked substation named Cass Pine in Bartow County that will interconnect between new Great Valley and Hill View 230kV substations.
TEAMS 20151 · plan p.114 · zone 211
GPC In the plan
p.9
Dec 31, 2026 No change Cass Pine, Great Valley, Hill View

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.