Grassy Hollow

Named in 1 project in the 2025 GA ITS Ten-Year Plan (2026-2035), in Bartow County.

Bartowcounty
230kV in the quote
GPCproject sponsor
1projects in the plan

Described as new. The quoted wording describes building this substation, without the word "new". “Build two 230kV switching stations (Hill View and Grassy Hollow)” — TEAMS 20150, plan p.121

County: “the Grassy Hollow–Great Valley 230 kV Transmission Project in Bartow County, which includes construction of a new Grassy Hollow substation” — Georgia Power, Grassy Hollow–Great Valley 230 kV Transmission Project page, retrieved 2026-11-20. The plan itself prints no county column.

Location

34.2449, -84.6749 · Bartow County, GA · view on a map

Point published by the utility. The utility publishes this point, on a project map or in a filing. Accurate to about ±300 m, as estimated by the research. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

How it was located: Printed by the sponsor: Georgia Power's Grassy Hollow–Great Valley project page embeds its project map's configuration, with a point marker titled "Grassy Hollow Substation" at 34.2448811, -84.67487111; the printed 230 kV route (64 vertices) runs from the Great Valley Substation marker and ends 50 m from it. Web-map marker, not a survey: the page says "MAP NOT BASED ON FIELD SURVEY DATA" and "Structure and Line Locations based on Pre-Engineering data and subject to change". ±300 m.

Sources: 2025 GA ITS Ten-Year Plan (2026-2035), Southern Company Services; filed by Georgia Power in GA PSC Docket 56002 (2025 Annual Transmission Update, public disclosure) (filed 2026-02-27), p.121 · Georgia Power, Grassy Hollow–Great Valley 230 kV Transmission Project page (n/a (retrieved 2026-11-20)), About the Project; Project Map · Georgia Power, Grassy Hollow - Great Valley pre-construction postcard (n/a), p. 1 · OpenStreetMap: 230 kV line McGrau Ford - Cartersville area (way 178742241) (OSM base 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
CC - HILL VIEW & GRASSY HOLLOW SUB - IMPROVEMENTS
Build two 230kV switching stations (Hill View and Grassy Hollow) looping into the Cartersville - McGrau Ford 230kV line. Build two new 230kV lines: Cass Pine - Great Valley and Great Valley - Grassy Hollow.
TEAMS 20150 · plan p.121 · zone 211
GPC In the plan
p.10
Jun 1, 2027 Advanced within 2027 Cartersville, Grassy Hollow, Hill View, McGrau Ford

Generation interconnection requests filed in Bartow, GA: Southern Company queue, 8 active of 17. Same county, not the same substation.

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.