Substation Scout

Cartersville

Named in 2 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
GPCproject sponsor
2projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
CC - HILL VIEW & GRASSY HOLLOW SUB - IMPROVEMENTS
Build two 230kV switching stations (Hill View and Grassy Hollow) looping into the Cartersville - McGrau Ford 230kV line. Build two new 230kV lines: Cass Pine - Great Valley and Great Valley - Grassy Hollow.
TEAMS 20150 · plan p.121 · zone 211
GPC In the plan
p.10
Jun 1, 2027 Advanced within 2027 Cartersville, Grassy Hollow, Hill View, McGrau Ford
CARTERSVILLE - EMERSON 230kV LINE REBUILD
Rebuild 5.3 mile of the Cartersville to Emerson 230kV line and replace limiting line elements
TEAMS 21292 · plan p.155 · zone 211
GPC In the plan
p.12
Jun 1, 2028 New project Cartersville, EMERSON

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.