Gabriel
Named in 8 listed projects in ERCOT’s transmission project tracking workbook, in Williamson County. First named in the release with data as of June 1, 2015.
Also printed as: Gabriel Substation
A HIFLD substation record has the same name and county: GABRIEL (WILLIAMSON County). The names agree; that does not confirm they are the same facility.
Generation interconnection requests filed in Williamson, TX: ERCOT queue, 1 active of 3. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| LCRATSC Aviation Substation Addition The new Aviation Substation will be constructed along LCRA TSC transmission line T359 Gabriel to Glasscock. Aviation will serve GUS customer load. ERCOT project 103271 |
LCRATSC Tier 4 |
Planned Future tab |
138 | May 2028 | Gabriel to Glasscock Williamson County |
Gabriel, Glasscock |
| LCRATSC Gabriel Rivery Transmission Line Upgrade LCRA TSC will upgrade T457 Gabriel - Rivery 138-kV transmission line to achieve a higher operational rating. The need for this project with identified by ERCOT in the EIR for RPG 25RPG009. ERCOT project 109790 · utility no. PLC-8540 · RPG 25RPG009 |
LCRATSC Tier 4 |
Planned Future tab |
138 | May 2029 | Gabriel to Rivery Williamson County |
Gabriel, Rivery |
| LCRATSC Gabriel Autotransformer Addition This project will construct a 345-kV yard adjacent to the Gabriel 138-kV yard and install two (2) 345/138-kV autotransformers; the new 345-kV yard will cut in to a new Hutto - Gabriel - Salado 345-kV double-circuit transmission line. The need for this project with identified by ERCOT in the EIR for RPG 25RPG009. ERCOT project 110118 · RTP 25RPG009 |
LCRATSC Tier 1 |
Planned Future tab |
345 | Dec 2031 | No terminals printed Williamson County |
Gabriel, Salado |
| LCRATSC Gabriel Hutto Transmission Line Addition This project will construct a new 345-kV double-circuit transmission line between Gabriel and Oncor Hutto substations. The need for this project with identified by ERCOT in the EIR for RPG 25RPG009. ERCOT project 110120 · RPG 25RPG009 |
LCRATSC Tier 1 |
Planned Future tab |
345 | Dec 2031 | Gabriel to Hutto Williamson County |
Gabriel, Hutto |
| LCRATSC Gabriel Salado Transmission Line Addition This project will construct a new 345-kV double-circuit transmission line between Gabriel and Oncor Salado substations. The need for this project with identified by ERCOT in the EIR for RPG 25RPG009. ERCOT project 110122 · RPG 25RPG009 |
LCRATSC Tier 1 |
Planned Future tab |
345 | Dec 2031 | Gabriel to Salado Switch Williamson / Bell County |
Gabriel, Salado Switch |
| This converts Bell County to Gabriel to 138 KV ERCOT project 75524 |
BEPC Tier 4 |
Planned Future tab |
138 | Nov 2027 | Bell County to Gabriel Bell / Williamson County |
Bell County, Gabriel |
| No title printed ERCOT project 86912 |
BEPC Tier 4 |
Planned Future tab |
138 | May 2027 | Gabriel to Schwertner Williamson County |
Gabriel, Schwertner |
| Gabriel - Rivery MLSE Upgrade Remove an MLSE on T457 Gabriel - Rivery 138-kV transmission line to achieve the full conductor rating. ERCOT project 92629 · RTP 2023-SC17 |
LCRATSC Tier 4 |
Planned Current-year planned tab |
138 | Jun 2026 | Gabriel Substation Williamson County |
Gabriel Substation |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 75524 | Moved between tabs | Current-year planned → Future |
| October 1, 2026 | 75524 | Projected in-service date | Dec 2026 → Nov 2027 |
| July 13, 2026 | 110118 | First listed | on the Future tab |
| July 13, 2026 | 109790 | First listed | on the Future tab |
| July 13, 2026 | 110120 | First listed | on the Future tab |
| July 13, 2026 | 110122 | First listed | on the Future tab |
| July 13, 2026 | 92629 | Projected in-service date | May 2026 → Jun 2026 |
| June 1, 2026 | 103271 | First listed | on the Future tab |
| February 1, 2026 | 75524 | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 86912 | Projected in-service date | Mar 2027 → May 2027 |
| February 1, 2026 | 92629 | Projected in-service date | Dec 2025 → May 2026 |
| October 1, 2025 | 92629 | Moved between tabs | Future → Current-year planned |
| October 1, 2025 | 92629 | Projected in-service date | May 2026 → Dec 2025 |
| June 1, 2025 | 92629 | First listed | on the Future tab |
| October 1, 2024 | 86912 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.