Williamson, TX interconnection queue
1 active project totalling 449 MW in the ERCOT queue, plus 2 with terminal status (shown greyed).
1active projects
449active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 27INR0606 | Big Watt Mustang Power | 138 | 449 | Gas | SS Completed, FIS Started, No IA |
| 23INR0210 | Cornwall Solar | n/r | 204.5 | Solar | Inactive |
| 24INR0244 | Cornwall BESS | n/r | 203.8 | Battery | Inactive |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.