Nacogdoches Southeast Switch

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Nacogdoches County. First named in the release with data as of June 1, 2015.

Nacogdochescounty as printed
138kV
ONCORutility
2projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Nacogdoches, TX: ERCOT queue, 3 active of 5 · SPP queue, 0 active of 4. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Rebuild Lufkin Switch - Nacogdoches Southeast Switch 138 kV Line
ERCOT project 109890 · utility no. R6062
ONCOR
Tier 1
Conceptual
Future tab
138 May 2029 Lufkin Switch to Nacogdoches Southeast Switch
Angelina / Nacogdoches County
Lufkin Switch, Nacogdoches Southeast Switch
Rebuild the Redland Switch - Nacogdoches Southeast Switch 138 kV Line
ERCOT project 109894 · utility no. R6538
ONCOR
Tier 1
Conceptual
Future tab
138 May 2030 Redland Switch to Nacogdoches Southeast Switch
Angelina / Nacogdoches County
Redland Switch, Nacogdoches Southeast Switch

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026109890First listedon the Future tab
July 13, 2026109894First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.