Substation Scout

Nacogdoches, TX interconnection queue

5 active projects totalling 1,002.7 MW in the ERCOT queue.

5active projects
1,002.7active MW
5total filed
Queue IDProjectkVMWResourceStatus
27INR0313 Spindletop Solar 345 286.4 Solar SS Completed, FIS Started, IA
27INR0228 Sunlit Pines BESS SLF 138 208.1 Battery SS Completed, FIS Started, No IA
27INR0226 Sunlit Pines Solar SLF 138 206.7 Solar SS Completed, FIS Started, No IA
26INR0161 Timberline Solar 345 201 Solar SS Completed, FIS Started, No IA
26INR0162 Timberline Storage 345 100.5 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.