Nacogdoches, TX interconnection queue

3 active projects totalling 587.9 MW in the ERCOT queue, plus 2 with terminal status (shown greyed).

3active projects
587.9active MW
5total filed
Queue IDProjectkVMWResourceStatus
27INR0313 Spindletop Solar 345 286.4 Solar SS Completed, FIS Completed, IA
27INR0228 Sunlit Pines BESS SLF 138 208.1 Battery Inactive
27INR0226 Sunlit Pines Solar SLF 138 206.7 Solar Inactive
26INR0161 Timberline Solar 345 201 Solar SS Completed, FIS Started, No IA
26INR0162 Timberline Storage 345 100.5 Battery SS Completed, FIS Started, No IA

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.