Lufkin Switch

Named in 4 listed projects in ERCOT’s transmission project tracking workbook, in Angelina County. First named in the release with data as of February 1, 2015.

Angelinacounty as printed
138, 345kV
ONCORutility
4projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Angelina, TX: ERCOT queue, 5 active of 5. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Rebuild Lufkin Switch - Nacogdoches Southeast Switch 138 kV Line
ERCOT project 109890 · utility no. R6062
ONCOR
Tier 1
Conceptual
Future tab
138 May 2029 Lufkin Switch to Nacogdoches Southeast Switch
Angelina / Nacogdoches County
Lufkin Switch, Nacogdoches Southeast Switch
Rebuild the Lufkin Switch - Stryker Creek Switch 138 kV Line
ERCOT project 109904 · utility no. R6040
ONCOR
Tier 1
Conceptual
Future tab
138 Dec 2030 Lufkin Switch to Stryker Creek Switch
Angelina / Cherokee County
Lufkin Switch, Stryker Creek Switch
Install Crockett Switch - Lufkin Switch 138 kV Line Ckt#2
ERCOT project 110002 · utility no. R6555
ONCOR
Tier 1
Conceptual
Future tab
138 May 2031 Crockett Switch to Lufkin Switch
Houston / Angelina County
Crockett Switch, Lufkin Switch
Lufkin Switch - Redland Switch 345 kV Line
Construct a new 345 kV Line from Lufkin Switch to Redland Switch
ERCOT project 5475 · utility no. R6077 · RPG 20RPG019
ONCOR
Tier 2
In-Service
Completed tab
345 Dec 2025
actual 2025-12
Lufkin Switch to Redland Switch
Angelina County
Lufkin Switch, Redland Switch

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 2026110002Status as reportedPlanned → Conceptual
July 13, 2026109890First listedon the Future tab
July 13, 2026109904First listedon the Future tab
July 13, 2026110002First listedon the Future tab
February 1, 20265475Moved between tabsFuture → Completed
February 1, 20265475Status as reportedPlanned → In-Service
February 1, 20265475Projected in-service dateDec 2026 → Dec 2025
October 1, 20255475Moved between tabsCurrent-year planned → Future
October 1, 20255475Projected in-service dateDec 2025 → Dec 2026
June 1, 20255475Moved between tabsFuture → Current-year planned

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.