Redland Switch

Named in 5 listed projects in ERCOT’s transmission project tracking workbook, in Angelina County. First named in the release with data as of October 1, 2020.

Angelinacounty as printed
138, 345kV
ONCORutility
5projects listed

Also printed as: Redland 138 kV Switch · Redland 345 kV Switch

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Angelina, TX: ERCOT queue, 5 active of 5. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Establish Redland Switch 345/138 kV Auto #2
ERCOT project 109851 · utility no. R6508
ONCOR
Tier 1
Conceptual
Future tab
345 May 2029 Redland 345 kV Switch to Redland 138 kV Switch
Angelina County
Redland 345 kV Switch
Rebuild the Redland Switch - Nacogdoches Southeast Switch 138 kV Line
ERCOT project 109894 · utility no. R6538
ONCOR
Tier 1
Conceptual
Future tab
138 May 2030 Redland Switch to Nacogdoches Southeast Switch
Angelina / Nacogdoches County
Redland Switch, Nacogdoches Southeast Switch
Rebuild Redland Switch - Kolb Lake Switch 138 kV Line
ERCOT project 109900 · utility no. R6509
ONCOR
Tier 1
Conceptual
Future tab
138 Dec 2030 Redland Switch to Kolb Lake Switch
Angelina County
Redland Switch, Kolb Lake Switch
Lufkin Switch - Redland Switch 345 kV Line
Construct a new 345 kV Line from Lufkin Switch to Redland Switch
ERCOT project 5475 · utility no. R6077 · RPG 20RPG019
ONCOR
Tier 2
In-Service
Completed tab
345 Dec 2025
actual 2025-12
Lufkin Switch to Redland Switch
Angelina County
Lufkin Switch, Redland Switch
Upgrade Redland Switch - Herty Tap 138 kV Line Section
ERCOT project 99624 · utility no. R6291
ONCOR
Tier 4
Planned
Future tab
138 May 2027 Redland 138 kV Switch to Herty Tap
Angelina County
Redland 138 kV Switch, Herty Tap

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202699624Projected in-service dateDec 2027 → May 2027
July 13, 2026109851First listedon the Future tab
July 13, 2026109894First listedon the Future tab
July 13, 2026109900First listedon the Future tab
June 1, 202699624Projected in-service dateMay 2027 → Dec 2027
February 1, 20265475Moved between tabsFuture → Completed
February 1, 20265475Status as reportedPlanned → In-Service
February 1, 20265475Projected in-service dateDec 2026 → Dec 2025
February 1, 202699624Projected in-service dateMay 2028 → May 2027
October 1, 20255475Moved between tabsCurrent-year planned → Future
October 1, 20255475Projected in-service dateDec 2025 → Dec 2026
October 1, 202599624First listedon the Future tab
June 1, 20255475Moved between tabsFuture → Current-year planned

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.