Redland Switch
Named in 5 listed projects in ERCOT’s transmission project tracking workbook, in Angelina County. First named in the release with data as of October 1, 2020.
Also printed as: Redland 138 kV Switch · Redland 345 kV Switch
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Angelina, TX: ERCOT queue, 5 active of 5. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Establish Redland Switch 345/138 kV Auto #2 ERCOT project 109851 · utility no. R6508 |
ONCOR Tier 1 |
Conceptual Future tab |
345 | May 2029 | Redland 345 kV Switch to Redland 138 kV Switch Angelina County |
Redland 345 kV Switch |
| Rebuild the Redland Switch - Nacogdoches Southeast Switch 138 kV Line ERCOT project 109894 · utility no. R6538 |
ONCOR Tier 1 |
Conceptual Future tab |
138 | May 2030 | Redland Switch to Nacogdoches Southeast Switch Angelina / Nacogdoches County |
Redland Switch, Nacogdoches Southeast Switch |
| Rebuild Redland Switch - Kolb Lake Switch 138 kV Line ERCOT project 109900 · utility no. R6509 |
ONCOR Tier 1 |
Conceptual Future tab |
138 | Dec 2030 | Redland Switch to Kolb Lake Switch Angelina County |
Redland Switch, Kolb Lake Switch |
| Lufkin Switch - Redland Switch 345 kV Line Construct a new 345 kV Line from Lufkin Switch to Redland Switch ERCOT project 5475 · utility no. R6077 · RPG 20RPG019 |
ONCOR Tier 2 |
In-Service Completed tab |
345 | Dec 2025 actual 2025-12 |
Lufkin Switch to Redland Switch Angelina County |
Lufkin Switch, Redland Switch |
| Upgrade Redland Switch - Herty Tap 138 kV Line Section ERCOT project 99624 · utility no. R6291 |
ONCOR Tier 4 |
Planned Future tab |
138 | May 2027 | Redland 138 kV Switch to Herty Tap Angelina County |
Redland 138 kV Switch, Herty Tap |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 99624 | Projected in-service date | Dec 2027 → May 2027 |
| July 13, 2026 | 109851 | First listed | on the Future tab |
| July 13, 2026 | 109894 | First listed | on the Future tab |
| July 13, 2026 | 109900 | First listed | on the Future tab |
| June 1, 2026 | 99624 | Projected in-service date | May 2027 → Dec 2027 |
| February 1, 2026 | 5475 | Moved between tabs | Future → Completed |
| February 1, 2026 | 5475 | Status as reported | Planned → In-Service |
| February 1, 2026 | 5475 | Projected in-service date | Dec 2026 → Dec 2025 |
| February 1, 2026 | 99624 | Projected in-service date | May 2028 → May 2027 |
| October 1, 2025 | 5475 | Moved between tabs | Current-year planned → Future |
| October 1, 2025 | 5475 | Projected in-service date | Dec 2025 → Dec 2026 |
| October 1, 2025 | 99624 | First listed | on the Future tab |
| June 1, 2025 | 5475 | Moved between tabs | Future → Current-year planned |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.