HERON

Named in 1 listed project in ERCOT’s transmission project tracking workbook. First named in the release with data as of February 1, 2024.

—county as printed
345kV
CNPutility
1projects listed

No HIFLD substation record has this name in this county.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
WA Parish 345kV Substation Expansion for Crowned Heron Storage (24INR0405)
Expand 345kV WA Parish substation for Crowned Heron Storage (24INR0405)
ERCOT project 76624
CNP
Tier 4
In-Service
Completed tab
345 Oct 2025
actual 2025-12
WA Parish to HERON
Harris County
WA Parish, HERON

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202676624Moved between tabsCurrent-year planned → Completed
February 1, 202676624Status as reportedPlanned → In-Service
October 1, 202576624Projected in-service dateSep 2025 → Oct 2025
June 1, 202576624Moved between tabsFuture → Current-year planned
June 1, 202576624Projected in-service dateAug 2025 → Sep 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.