North Belt
Named in 5 listed projects in ERCOT’s transmission project tracking workbook, in Harris County. First named in the release with data as of June 1, 2016.
A HIFLD substation record has the same name and county: NORTH BELT (HARRIS County). The names agree; that does not confirm they are the same facility.
Generation interconnection requests filed in Harris, TX: ERCOT queue, 30 active of 35 · MISO queue, 0 active of 1. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Upgrade Ckt.67B North Belt to DRILCO to increase thermal limits. ERCOT project 102540 |
CNP Tier 4 |
Planned Future tab |
138 | Dec 2027 | North Belt to DRILCO Harris County |
North Belt, DRILCO |
| DRILCO Area improvements in support of proposed load addition. Upgrade Substation equipment at DRILCO and North Belt to increase rating of ckt 67 ERCOT project 109847A |
CNP Tier 4 |
Conceptual Future tab |
138 | Jun 2027 | DRILCO to North Belt Harris County |
DRILCO, North Belt |
| This models upgrades required for a proposed load addition Install 345 kV substation. Loop 345 kV Circuit 97 Jordan to King into the new 345 kV substation. Install 200MVAR Cap Bank at new sub. ERCOT project 110090B |
CNP Tier 4 |
Conceptual Future tab |
345 | Jul 2029 | NEWSUB to Jordan/North Belt Harris County |
Jordan, North Belt |
| Facility Ratings Methodology Phase 2 (FRM2) Upgrades Upgrade Ckt.97A North Belt to TH Wharton to increase thermal limits as part of FRM2 upgrades. ERCOT project 99453D |
CNP Tier 4 |
In-Service Completed tab |
345 | May 2026 actual 2026-02 |
North Belt to TH Wharton Harris County |
North Belt, TH Wharton |
| Facility Ratings Methodology Phase 2 (FRM2) Upgrades Upgrade Ckt.97B King to North Belt to increase thermal limits as part of FRM2 upgrades. ERCOT project 99453E |
CNP Tier 4 |
Planned Future tab |
345 | May 2027 | King to North Belt Harris County |
King, North Belt |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 99453E | Moved between tabs | Current-year planned → Future |
| October 1, 2026 | 99453E | Projected in-service date | Oct 2026 → May 2027 |
| July 13, 2026 | 102540 | Projected in-service date | May 2027 → Dec 2027 |
| July 13, 2026 | 99453E | Projected in-service date | Jun 2026 → Oct 2026 |
| July 13, 2026 | 109847A | First listed | on the Future tab |
| July 13, 2026 | 110090B | First listed | on the Future tab |
| July 13, 2026 | 99453E | Projected in-service date | May 2026 → Jun 2026 |
| June 1, 2026 | 99453D | Moved between tabs | Current-year planned → Completed |
| June 1, 2026 | 99453D | Status as reported | Planned → In-Service |
| February 1, 2026 | 102540 | First listed | on the Future tab |
| February 1, 2026 | 99453D | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 99453E | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 99453E | Projected in-service date | Oct 2029 → May 2026 |
| October 1, 2025 | 99453D | First listed | on the Future tab |
| October 1, 2025 | 99453E | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.