Jordan
Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Harris County. First named in the release with data as of July 13, 2026.
Harriscounty as printed
345kV
CNPutility
3projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Harris, TX: ERCOT queue, 30 active of 35 · MISO queue, 0 active of 1. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| This models upgrades required for a proposed load addition Install 345 kV substation. Loop 345 kV Circuit 97 Jordan – King into the new 345 kV substation. ERCOT project 110090A |
CNP Tier 4 |
Conceptual Future tab |
345 | Oct 2027 | NEWSUB to Jordan/King Harris County |
Jordan, King |
| This models upgrades required for a proposed load addition Install 345 kV substation. Loop 345 kV Circuit 97 Jordan to King into the new 345 kV substation. Install 200MVAR Cap Bank at new sub. ERCOT project 110090B |
CNP Tier 4 |
Conceptual Future tab |
345 | Jul 2029 | NEWSUB to Jordan/North Belt Harris County |
Jordan, North Belt |
| This models upgrades required for a proposed load addition Increase the size of the first 345 kV capacitor at NEWSUB bank from 200 MVAR to 300 MVAR. Add second 300MVAR capacitor bank. ERCOT project 110090C |
CNP Tier 4 |
Conceptual Future tab |
345 | Jul 2031 | NEWSUB to Jordan/King Harris County |
Jordan, King |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| July 13, 2026 | 110090A | First listed | on the Future tab |
| July 13, 2026 | 110090B | First listed | on the Future tab |
| July 13, 2026 | 110090C | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.