Named in 12 listed projects in ERCOT’s transmission project tracking workbook, in Brazoria County. First named in the release with data as of February 1, 2023.
Brazoriacounty as printed
138kV
CNPutility
12projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Brazoria, TX: ERCOT queue, 54 active of 63. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Upgrade ckt26 from Angleton to CAMDEN and ckt82 from Angleton to Oyster Creek to increase thermal limits. Upgrade Ckt.26 STRATT to Clute to increase thermal limits. ERCOT project 109575C · RPG 26RPG012 |
CNP Tier 3 |
Planned Future tab |
138 | May 2029 | STRATT to Clute Brazoria County |
STRATT, Clute |
| Upgrade ckt26 from Angleton to CAMDEN and ckt82 from Angleton to Oyster Creek to increase thermal limits. Upgrade Ckt.26 Clute to SINTEK to increase thermal limits. ERCOT project 109575D · RPG 26RPG012 |
CNP Tier 3 |
Planned Future tab |
138 | May 2029 | Clute to SINTEK Brazoria County |
Clute, SINTEK |
| Upgrade ckt26 from Angleton to CAMDEN and ckt82 from Angleton to Oyster Creek to increase thermal limits. Upgrade Ckt.82C Angleton to RIWOOD to increase thermal limits. ERCOT project 109575E · RPG 26RPG012 |
CNP Tier 3 |
Planned Future tab |
138 | May 2029 | Clute to SINTEK Brazoria County |
Clute, SINTEK |
| Upgrade ckt26 from Angleton to CAMDEN and ckt82 from Angleton to Oyster Creek to increase thermal limits. Upgrade Ckt.82 RIWOOD to Clute to increase thermal limits. ERCOT project 109575F · RPG 26RPG012 |
CNP Tier 3 |
Planned Future tab |
138 | May 2029 | Clute to SINTEK Brazoria County |
Clute, SINTEK |
| Upgrade ckt26 from Angleton to CAMDEN and ckt82 from Angleton to Oyster Creek to increase thermal limits. Upgrade Ckt.82 Clute to CAVERN to BIPORT to increase thermal limits. ERCOT project 109575G · RPG 26RPG012 |
CNP Tier 3 |
Planned Future tab |
138 | May 2029 | CAVERN to Clute/BIPORT Brazoria County |
CAVERN, Clute, BIPORT |
| Clute 138kV Switching Station Reconfigure existing Ckt.82F RIWOOD to CAVERN to BIPORT and loop into new CEHE-owned 138kV Clute switching station to create new Ckt.82 RIWOOD to Clute to CAVERN to BIPORT. ERCOT project 72044A · RPG 22RPG038 |
CNP Tier 3 |
Planned Future tab |
138 | Mar 2028 | Clute to RIWOOD/CAVERN Brazoria County |
Clute, RIWOOD, CAVERN |
| Clute 138kV Switching Station ERCOT project 72044B · RPG 22RPG038 |
CNP Tier 3 |
Planned Current-year planned tab |
138 | Dec 2026 | No terminals printed Brazoria County |
Clute |
| Clute 138kV Switching Station Reconfigure existing Ckt.26D STRATT to SINTEK and loop into new CEHE-owned 138kV Clute switching station to create new Ckt.26 STRATT to Clute to SINTEK. ERCOT project 72044C · RPG 22RPG038 |
CNP Tier 3 |
Planned Future tab |
138 | Mar 2028 | Clute to SINTEK Brazoria County |
Clute, SINTEK |
| Clute 138kV Switching Station ERCOT project 72044D · RPG 22RPG038 |
CNP Tier 3 |
Planned Current-year planned tab |
138 | Dec 2026 | No terminals printed Brazoria County |
Clute |
| Samaritan 138kV Switching Station Connect Samaritan CEHE substation with two leads to TNMP_White Oak distribution substation. ERCOT project 75776B |
CNP Tier 4 |
Planned Future tab |
138 | May 2027 | Samaritan to Angleton/Clute Brazoria County |
Samaritan, Angleton, Clute |
| Upgrade Ckt.26 STRATT to SINTEK to increase thermal limits. Upgrade Ckt.26F Velasco to CAMDEN to increase thermal limits. Upgrade Ckt.26D Clute to SINTEK to increase thermal limits. (Expect a full 2-959ACSS reconductor Ckt.26 Clute to SINTEK and a 1-795AAC conductor limitation Ckt.26 STRATT to Clute) ERCOT project 85987A · RPG 24RPG012 |
CNP Tier 3 |
Planned Future tab |
138 | May 2027 | Clute to SINTEK Brazoria County |
Clute, SINTEK |
| Clute to Velasco Ckt.82 Upgrades RPG Upgrade Ckt.82F RIWOOD to CAVERN to BIPORT to increase thermal limits. (Expect partial reconductor to Ckt.86F RIWOOD to CAVERN with 1-795ACSR limiting conductor and full 2-959ACSS reconductor to Ckt.86F CAVERN to BIPORT) ERCOT project 90242B · RPG 24RPG012 |
CNP Tier 4 |
Planned Future tab |
138 | May 2027 | CAVERN to Clute/BIPORT Brazoria County |
CAVERN, Clute, BIPORT |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 72044A | Projected in-service date | Dec 2027 → Mar 2028 |
| October 1, 2026 | 72044C | Projected in-service date | Dec 2027 → Mar 2028 |
| July 13, 2026 | 109575C | First listed | on the Future tab |
| July 13, 2026 | 109575D | First listed | on the Future tab |
| July 13, 2026 | 109575E | First listed | on the Future tab |
| July 13, 2026 | 109575F | First listed | on the Future tab |
| July 13, 2026 | 109575G | First listed | on the Future tab |
| July 13, 2026 | 75776B | Moved between tabs | Current-year planned → Future |
| July 13, 2026 | 75776B | Projected in-service date | Oct 2026 → May 2027 |
| June 1, 2026 | 72044A | Moved between tabs | Current-year planned → Future |
| June 1, 2026 | 72044A | Projected in-service date | Dec 2026 → Dec 2027 |
| June 1, 2026 | 72044C | Moved between tabs | Current-year planned → Future |
| June 1, 2026 | 72044C | Projected in-service date | Dec 2026 → Dec 2027 |
| February 1, 2026 | 72044A | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 72044B | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 72044C | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 72044D | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 75776B | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 75776B | Projected in-service date | Feb 2026 → Oct 2026 |
| February 1, 2026 | 85987A | Projected in-service date | May 2026 → May 2027 |
| February 1, 2026 | 90242B | Projected in-service date | May 2026 → May 2027 |
| October 1, 2025 | 75776B | Moved between tabs | Current-year planned → Future |
| October 1, 2025 | 75776B | Projected in-service date | Oct 2025 → Feb 2026 |
| June 1, 2025 | 72044A | Projected in-service date | May 2026 → Dec 2026 |
| June 1, 2025 | 72044B | Projected in-service date | May 2026 → Dec 2026 |
| June 1, 2025 | 72044C | Projected in-service date | May 2026 → Dec 2026 |
| June 1, 2025 | 72044D | Projected in-service date | May 2026 → Dec 2026 |
| June 1, 2025 | 75776B | Moved between tabs | Future → Current-year planned |
| February 1, 2025 | 90242B | First listed | on the Future tab |
| October 1, 2024 | 75776B | Projected in-service date | May 2025 → Oct 2025 |
| October 1, 2024 | 85987A | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.