Samaritan

Named in 4 listed projects in ERCOT’s transmission project tracking workbook, in Brazoria County. First named in the release with data as of October 1, 2023.

Brazoriacounty as printed
138kV
CNPutility
4projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Brazoria, TX: ERCOT queue, 54 active of 63. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Upgrade ckt26 from Angleton to CAMDEN and ckt82 from Angleton to Oyster Creek to increase thermal limits.
Upgrade Ckt.26C Angleton to Samaritan to increase thermal limits.
ERCOT project 109575A · RPG 26RPG012
CNP
Tier 3
Planned
Future tab
138 May 2029 Angleton to Samaritan
Brazoria County
Angleton, Samaritan
Upgrade ckt26 from Angleton to CAMDEN and ckt82 from Angleton to Oyster Creek to increase thermal limits.
Upgrade Ckt.26I Samaritan to STRATT to increase thermal limits.
ERCOT project 109575B · RPG 26RPG012
CNP
Tier 3
Planned
Future tab
138 May 2029 Samaritan to STRATT
Brazoria County
Samaritan, STRATT
Samaritan 138kV Switching Station
Reconfigure Ckt.26C Angleton to STRATT and loop into new CEHE-owned 138kV Samaritan switching station to create new Ckt.26 Angleton to Samaritan to STRATT. No line upgrades Ckt.26 Angleton to Samaritan to STRATT.
ERCOT project 75776A
CNP
Tier 4
Planned
Future tab
138 May 2027 Samaritan to Angleton/STRATT
Brazoria County
Samaritan, Angleton, STRATT
Samaritan 138kV Switching Station
Connect Samaritan CEHE substation with two leads to TNMP_White Oak distribution substation.
ERCOT project 75776B
CNP
Tier 4
Planned
Future tab
138 May 2027 Samaritan to Angleton/Clute
Brazoria County
Samaritan, Angleton, Clute

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026109575AFirst listedon the Future tab
July 13, 2026109575BFirst listedon the Future tab
July 13, 202675776AMoved between tabsCurrent-year planned → Future
July 13, 202675776AProjected in-service dateOct 2026 → May 2027
July 13, 202675776BMoved between tabsCurrent-year planned → Future
July 13, 202675776BProjected in-service dateOct 2026 → May 2027
February 1, 202675776AMoved between tabsFuture → Current-year planned
February 1, 202675776AProjected in-service dateFeb 2026 → Oct 2026
February 1, 202675776BMoved between tabsFuture → Current-year planned
February 1, 202675776BProjected in-service dateFeb 2026 → Oct 2026
October 1, 202575776AMoved between tabsCurrent-year planned → Future
October 1, 202575776AProjected in-service dateOct 2025 → Feb 2026
October 1, 202575776BMoved between tabsCurrent-year planned → Future
October 1, 202575776BProjected in-service dateOct 2025 → Feb 2026
June 1, 202575776AMoved between tabsFuture → Current-year planned
June 1, 202575776BMoved between tabsFuture → Current-year planned
October 1, 202475776AProjected in-service dateMay 2025 → Oct 2025
October 1, 202475776BProjected in-service dateMay 2025 → Oct 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.