Substation Scout

CAVERN

Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Brazoria County. First named in the release with data as of February 1, 2024.

Brazoriacounty as printed
138kV
CNPutility
3projects listed

A HIFLD substation record has the same name and county: CAVERN (BRAZORIA County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Brazoria, TX: ERCOT queue, 54 active of 63. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Upgrade ckt26 from Angleton to CAMDEN and ckt82 from Angleton to Oyster Creek to increase thermal limits.
Upgrade Ckt.82 Clute to CAVERN to BIPORT to increase thermal limits.
ERCOT project 109575G · RPG 26RPG012
CNP
Tier 3
Planned
Future tab
138 May 2029 CAVERN to Clute/BIPORT
Brazoria County
CAVERN, Clute, BIPORT
Clute 138kV Switching Station
Reconfigure existing Ckt.82F RIWOOD to CAVERN to BIPORT and loop into new CEHE-owned 138kV Clute switching station to create new Ckt.82 RIWOOD to Clute to CAVERN to BIPORT.
ERCOT project 72044A · RPG 22RPG038
CNP
Tier 3
Planned
Future tab
138 Mar 2028 Clute to RIWOOD/CAVERN
Brazoria County
Clute, RIWOOD, CAVERN
Clute to Velasco Ckt.82 Upgrades RPG
Upgrade Ckt.82F RIWOOD to CAVERN to BIPORT to increase thermal limits. (Expect partial reconductor to Ckt.86F RIWOOD to CAVERN with 1-795ACSR limiting conductor and full 2-959ACSS reconductor to Ckt.86F CAVERN to BIPORT)
ERCOT project 90242B · RPG 24RPG012
CNP
Tier 4
Planned
Future tab
138 May 2027 CAVERN to Clute/BIPORT
Brazoria County
CAVERN, Clute, BIPORT

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202672044AProjected in-service dateDec 2027 → Mar 2028
July 13, 2026109575GFirst listedon the Future tab
June 1, 202672044AMoved between tabsCurrent-year planned → Future
June 1, 202672044AProjected in-service dateDec 2026 → Dec 2027
February 1, 202672044AMoved between tabsFuture → Current-year planned
February 1, 202690242BProjected in-service dateMay 2026 → May 2027
June 1, 202572044AProjected in-service dateMay 2026 → Dec 2026
February 1, 202590242BFirst listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first