Linwood

Named in 3 PJM planning documents for 3 projects, from March 13, 2025 to November 4, 2025.

Not stateddescribed as
DPLzone
230 kVkV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
DPL Transmission Zone: b3143 Scope and Cost Change
b3143
Not printed $21M 10/31/2026 Not printed 2025-03-13
SRRTEP Mid-Atlantic
Claymont Substation Bus Upgrade
b4004.1
Not printed $0.031M 06-01-2030 Not printed 2025-11-04
TEAC
Claymont Substation Bus Upgrade Not printed $0.031M 06-01-2030 Not printed 2025-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$5.5 M → $21M 2025-03-13 2025-03-13

Every mention

DateDocumentProjectWhat the document says about it
2025-11-04 TEAC
Item 14 - Reliability Analysis Update p. 14
Claymont Substation Bus Upgrade No role wording
230 kV
2025-10-08 TEAC
Item 13 - Reliability Analysis Update p. 14
Claymont Substation Bus Upgrade No role wording
230 kV
2025-03-13 SRRTEP Mid-Atlantic
Item 01 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 3
DPL Transmission Zone: b3143 Scope and Cost Change No role wording
230 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.