Substation Scout

Topaz

Named in 1 PJM planning document for 1 project, on November 4, 2025.

Newdescribed as
DOMzone
—kV as printed
1mentions

Described as new: “new substation (Topaz)” — source, page 5

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dominion Transmission Zone: Supplemental Customer Load Request
DOM-2025-0007
Not printed Not printed 10/1/2030 300 MW 2025-11-04
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2025-11-04 TEAC
Item 13 - DOM Supplemental Projects p. 5
Dominion Transmission Zone: Supplemental Customer Load Request “new substation (Topaz)”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this