Slayden Creek

Named in 2 PJM planning documents for 1 project, from March 10, 2026 to October 6, 2026.

Newdescribed as
DOMzone
230 kVkV as printed
2mentions

Described as new: “new 230 kV delivery point (Slayden Creek)” — source, page 57

Also printed as: Slayden Creek Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Slayden Creek 230kV Delivery - DEV
DOM-2024-0004 · s3994
Conceptual $ 26M 12/1/2029 300 MW 2026-10-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 57
Slayden Creek 230kV Delivery - DEV “new 230 kV delivery point (Slayden Creek)”
230 kV
2026-03-10 TEAC
Item 09 - DOM Supplemental Projects p. 8
Slayden Creek 230kV Delivery - DEV “Slayden Creek Substation will be constructed”
230 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.