Substation Scout

Skiffes Creek

Named in 1 PJM planning document for 1 project, on October 6, 2026.

Not stateddescribed as
DOMzone
—kV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Line #209 and Line #58 Partial Rebuild
DOM-2021-0006 · s2623
Engineering $66.89M 05/30/2029 46.6MW 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$19.5M → $66.89M 2026-10-06 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 46
Line #209 and Line #58 Partial Rebuild No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this