Substation Scout

Simms

Named in 1 PJM planning document for 1 project, on April 7, 2026.

Newdescribed as
DOMzone
230kVkV as printed
1mentions

Described as new: “new substation (Simms)” — source, page 4

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dominion Transmission Zone: Supplemental Customer Load Request
DOM-2026-0015
Not printed Not printed 12/01/2029 296MW 2026-04-07
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-04-07 TEAC
Item 09 - DOM Supplemental Projects p. 4
Dominion Transmission Zone: Supplemental Customer Load Request “new substation (Simms)”
230kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this