Stafford, VA interconnection queue

2 active projects totaling 252.9 MW in the PJM queue, plus 3 with terminal status (shown grayed).

2active projects
252.9active MW
5total filed
Queue IDProjectkVMWResourceStatus
C01-1024 Not reported n/r 250 Battery Withdrawn
C01-1240 Garrisonville 230 kV 230 250 Battery Active
T10 Stafford Regional LF 34.5 3 Gas Deactivated
C01-1210 Cranes Corner 34.5 kV 34.5 2.9 Solar Active
Q71 Strafford Regional LF 13.2 2 Gas Deactivated

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.