Substation Scout

Stafford, VA interconnection queue

2 active projects totalling 252.9 MW in the PJM queue, plus 3 with terminal status (shown greyed).

2active projects
252.9active MW
5total filed
Queue IDProjectkVMWResourceStatus
C01-1024 Not reported n/r 250 Battery Withdrawn
C01-1240 Garrisonville 230 kV 230 250 Battery Active
T10 Stafford Regional LF 34.5 3 Gas Deactivated
C01-1210 Cranes Corner 34.5 kV 34.5 2.9 Solar Active
Q71 Strafford Regional LF 13.2 2 Gas Deactivated

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.