Substation Scout

Raines

Named in 4 PJM planning documents for 3 projects, from October 8, 2024 to October 8, 2025.

Newdescribed as
DOMzone
230kVkV as printed
6mentions

Described as new: “Construct Raines 230kV substation” — source, page 39

Also printed as: Raines Sub · Raines 230kV substation · Raines Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Evans Creek 230kV Delivery - DEV
DOM-2022-0027 · s3021
Engineering $30.0M 08/01/2025 126.0 MW 2024-10-08
TEAC
Raines 230kV Delivery - DEV
DOM-2022-0029 · s3023
Engineering $20.0M 08/01/2025 37.0 MW 2024-10-08
TEAC
Dominion Transmission Zone: Supplemental Customer Load Request
DOM-2024-0054 · s3686
Engineering $48.6M 11/01/2028 26 MW 2025-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Southern
Dominion p. 35
Evans Creek 230kV Delivery - DEV No role wording
2026-09-08* SRRTEP Southern
Dominion p. 39
Raines 230kV Delivery - DEV “Construct Raines 230kV substation”
230kV
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 61
Dominion Transmission Zone: Supplemental Customer Load Request No role wording
230kV
2025-05-06 TEAC
Item 09 - DOM Supplemental Projects p. 12
Dominion Transmission Zone: Supplemental Customer Load Request No role wording
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 35
Evans Creek 230kV Delivery - DEV No role wording
230kV
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 39
Raines 230kV Delivery - DEV “Construct Raines 230kV substation”
230kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.