Substation Scout

New Road

Named in 1 PJM planning document for 1 project, on September 8, 2026.

Not stateddescribed as
DOMzone
230-115 kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Operational Flexibility and Efficiency
DOM-2026-0037
Not printed Not printed Not printed Not printed 2026-09-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08 TEAC
Item 10 - DOM Supplemental Projects p. 4
Operational Flexibility and Efficiency No role wording
230-115 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.