Bishop

Named in 2 PJM planning documents for 1 project, on October 8, 2024.

Newdescribed as
DOMzone
115kVkV as printed
2mentions

Described as new: “Construct a new substation” — source, page 148

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Bishop Sub – 115kV Delivery – MEC
DOM-2023-0041 · s3081
Engineering $15.0 M 01/01/2025 48 MW 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Southern
Dominion p. 148
Bishop Sub – 115kV Delivery – MEC “Construct a new substation”
115kV
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 147
Bishop Sub – 115kV Delivery – MEC “Construct a new substation”
115kV